On the esplanade, the last concrete pour section remains to be completed, and workers will be on site this week and the tar tie to the existing road is complete.

In Sinclair Street north, paving of parking bays on the east side has started and the pavement has been excavated and tarred.

Drainage on the east side is complete but is still progressing on the west side.

On East Princes Street, paving of the parking bays, drainage, and ducting on the north side is complete.

The railway entrance and exit pends setts (concrete slabs) is complete and the bus stop foundation is complete.

However, the excavation of pavements on the north side is ongoing Drainage, cabling, kerbing to both the east and west side has all been completed in Colquhoun Street north, but paving to parking bays and pavements on the east side ongoing.