SUPPLY issues in the construction industry could push Helensburgh’s new leisure centre over budget, key figures involved in the project have admitted

The scheme’s project manager has also told local councillors that contractors on site have been waiting four to five weeks for a delivery of concrete, although the impact on the schedule is currently unknown.

The new leisure centre is currently scheduled to open in August 2022, with work having progressed on its site behind the town’s current swimming pool for several months.

A report on its progress went before councillors at a virtual meeting of Argyll and Bute Council’s Helensburgh and Lomond area committee on Thursday, June 17.

At the meeting, Councillor Richard Trail (SNP, Helensburgh and Lomond South) questioned whether delivery issues had been experienced.

He said: “Can you tell me if there have been any issues with getting deliveries of materials to the site? I know with the construction industry that some areas have been experiencing real difficulty.”

READ MORE: 'Topping out' ceremony marks completion of new Helensburgh leisure centre's structure and roof

Project manager Andrew Collins replied: “Until about two to three weeks ago we had not encountered any real issues. Concrete and steel deliveries and other deliveries for the site have been fine for the first 40-plus weeks.

“But we are now starting to encounter problems with materials around timber, concrete and cement, along with some other items.

“There are now longer waiting times and we are monitoring that very closely with the contractors to see how it is going to affect the programme of delivery.”

Councillor Trail then followed up by saying: “It might also affect the budget, because prices of materials are going up quickly now.”

Mr Collins responded: “We are in discussions with the contractor on what effect that may have. For example, we have waited four to five weeks for a concrete delivery to complete the concrete on the eastern slipway.

“I am sure we will encounter supply problems going forward.”

READ MORE: Developers say they're making 'tremendous progress' on site of Helensburgh's waterfront leisure centre

Councillor Gary Mulvaney (Conservative, Helensburgh Central), the local authority’s policy lead for financial services and major projects, then said: “I was speaking to somebody else unconnected to this project about timber costs going up by about 30 per cent in the last five to six months.

“Not only is there a shortage but there are issues with lack of supply from northern Scandinavia, and everybody doing building and home extensions.

“So we are fortunate in that we do not have a high timber content within the building.

“However, Andrew is right – other supply costs will push our costs up.

“At the moment we are right to say we are within budget and we just have to keep as tight a hold on that as possible.

“As we go into the internal fittings, with more contractors on site, we might see more exposure to what is happening in the market. We will wait and see what happens.”

READ MORE: Stay in touch with the latest Helensburgh and Lomond news headlines by clicking here